View Procedure
Procedure Name | Mining Lease |
Description |
Required Documents
No.
|
Type of documents
|
Note
|
1
|
Applicant Identification
|
|
2
|
Information on applicant financial status
|
|
3
|
Information on applicant’s technical experience and competence
|
|
4
|
Information on proposed project
|
Project Proposal
|
5
|
Police clearance
|
|
6
|
Mining lease application form- Form C
|
|
Process Steps
Step 1
|
Collect Mining lease application form Commissioner of Mines
|
Step 2
|
Identify Mining site
|
Step 3
|
Commissioner of Mines (Site visit done by Commissioner of mines within 14 days)
|
Step 4
|
Notify applicant if site viable or not
|
Step 5
|
If not viable identify another site if viable applicant completes the application form and submit to Commissioner
|
Step 7
|
Technical Evaluation by Commissioner of Mines if approved Move it Mining Board
|
Step 8
|
Final Evaluation by Mining Board (3 months)
|
Step 9
|
Notification to applicant (Approved pending Environmental Impact assessment EIA)
|
Step 10
|
Submit Environmental Clearance
|
Step 11
|
Issuance of License
|
Step 12
|
Applicant register license with Registry of Deeds office
|
Step 13
|
Return Copy Registered License to Commissioner of Mines
|

|
Category | Procedures |
The following form/s are used in this procedure
This procedure applies to the following measures
Name | Measure Type | Agency | Description | Comments | Legal Document | Validity To | Measure Class |
No results found. |